SiteIQ shows two independent BESS investigation prompts from mapped substation distance — shared-interconnection fit and a distance-based cue to look at curtailment/export — plus an illustrative MW/MWh band from screened PV capacity. Neither measures grid capacity, curtailment, or battery economics.

Two separate signals

SiteIQ answers two different BESS questions from the same grid-proximity rating. They can point opposite ways on the same site — that is intentional, not a bug.

1. Co-location fit (shared interconnection)

Does adding storage help share the interconnection infrastructure you are already building? Fit comes from the OpenStreetMap nearest-substation rating:

2. Curtailment / export investigation cue

Longer mapped distance is only a prompt to investigate whether the interconnection may be weak or export-constrained — it does not prove curtailment, grid strength, or storage value. The cue moves roughly opposite to co-location fit:

Example: a site ~12 km from the nearest mapped substation scores Limited on co-location fit and High on the investigation cue — both are distance-based labels, not measured grid capacity.

The illustrative MW / MWh range is a rule-of-thumb fraction of the SiteIQ screened PV capacity band (not LayoutIQ packed DC). Agri-PV projects also get a land-use note: dual-use leases may restrict non-agricultural equipment siting.

What it is not

Confirm storage with the DSO/TSO and a qualified BESS engineer before committing to a configuration. OSM substations can be incomplete; treat distance as a screening heuristic.